To verify if the placement of a lesson does not respect the constraints of a subject, a teacher, a class or the hourly maximum of a resource:

  1. From the display Timetable of one of the resources, select the lesson and click on it to switch to diagnostic mode.
  2. Move the green frame to the wanted slot: 
    • If the Weekly Hourly Maximum of a resource is exceeded, the symbol  is displayed on the front on the lesson form.
    • If the Daily Hourly Maximum of a resource is exceeded, the symbol  is displayed on the front on the lesson form.
    • If the Maximum number of days of presence per year of a resource is exceeded, the symbol  is displayed on the front on the lesson form.
    • If the Maximum number of days of presence per week of a resource is exceeded, the symbol  is displayed on the front on the lesson form.
    • If the subject incompatibility is not respected, the symbol is displayed in front of the concerned resource.
    • If the previous lesson or the following lesson is on another site and that the travel time is not respected, the symbol is displayed in front of the concerned resource.
    • If the lesson encroaches on the inter-lesson, a symbol is displayed on the price sheet, in front of the concerned resource.
    • If one of the resources is unavailable on this slot, a pale red square  is displayed in front.